Repair work on Weymouth harbour ferry berth struck with delays

DELAYS: Weymouth harbour’s ferry berth DELAYS: Weymouth harbour’s ferry berth

WORK to repair Weymouth harbour’s ferry berth has been hit by delays.

Council chiefs are facing a race against time to get the quay ready for the return of Condor Ferries which is planning to restart cross-Channel sailings in July.

Noisy work to drive in piles, to form deep foundations, was due to start a month ago but has yet to happen.

Weymouth and Portland Borough Council confirmed there had been problems getting the old piles out, delaying the project.

Despite this, the council says it is still on track to complete the project in time for summer.

It will not have to find additional money as a contingency fund was set aside anticipating such problems.

The project completion date is scheduled to be May.

The council agreed a £3.9million project to fix the berth last year after the state of the crumbling quay became apparent and Condor switched its sailings to Poole.

Condor, Weymouth port’s biggest customer pumping millions into the local economy, says it will return as long as works are completed.

Contractor Balfour Beatty has been appointed to carry out the work.

Borough council environment spokesman Ian Roebuck, pictured, said: “Right from the start we recognised there were a number of project risks such as complications removing the old piles, obstructions when driving new piles in and poor weather which could result in changes to the timetable.

“So the contract has built into it a contingency margin of both cost and timetable.

“Some of these risks have materialised, with difficulties experienced with the pile extraction process.

“Additional piles have also been found that require removal and this has impacted the sequencing of the programme.

“At the present time the additional works are contained within the contract contingency fund and overall programme.

“The council’s effective project management is minimising the effect of these risks.”

Coun Roebuck added: “The project is on budget and we are on track to complete the works in time for Condor Ferries to return to the borough as planned on July 17.

 

“But we are not complacent – there is still a large amount of work to do and working in the marine environment always presents additional difficulties.”

Former Weymouth harbourmaster Peter Tambling suggested a number of factors could be to blame for the difficulties in extracting the piles.

These include the build-up of silt in the harbour washed down river, a tenacious bank of Oxford clay at the harbour entrance, and the coastal drift of material from westwards from St Alban’s Head.

Comments(5)

Mr_Blue_Sky says...
10:39am Mon 4 Mar 13

So they anticipated these problems and factored them into the price and time.

Surely this is a non-story....

sparkleeye says...
11:08am Mon 4 Mar 13

I presume these are private contractors having the problems? private ones who surveyed the job beforehand then made a bid for a price for the job? So why does extra money have to be factored in for any time after the bid price has been made?

stench says...
12:54pm Mon 4 Mar 13

how stupid are the above two people?

JamesYoung says...
1:05pm Mon 4 Mar 13

I think Mr Blue Sky is spot on.
They negotiated a contract which allowed for contingency. That's good practice. There's no story here.

Just-an-Opinion says...
10:30am Tue 5 Mar 13

All reports have stated that the cost of the repair is 3.92m but the story above now states there is a contingency fund. Is the contingency fund additional costs?? Is there the possibility of the overall cost reducing if the contingency fund isn't required?? It appears that the overall cost never was going to be 3.92m and there are hidden costs!

click2find

About cookies

We want you to enjoy your visit to our website. That's why we use cookies to enhance your experience. By staying on our website you agree to our use of cookies. Find out more about the cookies we use.

I agree